Benton County PUD Kennewick, WA

JH Kelly was awarded an Engineering, Procurement and Construction contract for a simple cycle 27.5 MW peaking plant for the Benton County Public Utility District. Located in Kennewick, Washington, using Pratt & Whitney FT-8 gas turbine technology, Kelly performed all civil, structural, mechanical and electrical design, procured all BOP equipment and performed all construction activities. The unit was brought in on line approximately six months from receipt of notice to proceed. JH Kelly also assisted with start-up and commissioning activities. Special points of interest: - Teamed with Power Engineers
- 27.5 MW peaking plant
| | | | | | To print pdf version |
|